By Cheryl Dowden, December 27, 2019
Definition of “high” hazard dams
Dams are considered “high” hazard, regardless of current conditions, if their failure has the potential to cause death.
The Federal Guidelines for Dam Safety outlines a customary classification practice among both federal and state dam safety offices regarding the phrase, “high hazard dams”. This practice “is to classify a dam according to the potential impact a dam failure (breach) or mis-operation (unscheduled release) would have on upstream and/or downstream areas or at locations remote from the dam.”
Federal Guidelines for Dam Safety – Hazard Potential Classification System for Dams
federal-guidelines-for-dam-safety-hazard-potential-classification-system-for-damsArticle states there are issues with Lake Cortez Dam
According to the Arkansas Democrat-Gazette, “of the 114 high hazard dams in Arkansas, 23 are rated in ‘poor’ or ‘unsatisfactory’ condition.” Per this article, the dam at Lake Cortez is on this list, but don’t get too excited just yet.
If a “high hazard dam” catastrophically fails, there is a potential for major property damage and potential loss of life.
The Arkansas Natural Resources Commission recently cited Hot Springs Village for both vegetation and spillway issues. The AR NRC is funded through FEMA.
The engineer report in the pdf below this paragraph grades Lake Cortez Dam as “acceptable”. This information conflicts with the letter HSV received from the AR NRC which graded the Lake Cortez Dam as being in “good” condition (see chart below the engineer report).
Lake Cortez Dam Engineer Report – Arkansas Natural Resources Commission
Cortez-Dam-Engineer-Report-2019Due to the size of the chart below, I had to use two screenshots. The second screenshot should be visualized as the right-hand side of the first. 1979 is the year Lake Cortez Dam was completed. 857 is the crest length of the dam in feet and 80 is the height in feet.
Hot Springs Village Chief Operating Officer, Jason Temple, has stated that we have corrected the vegetation issues, but not the rehab on the spillways. The following is a partial transcript from the December 18, 2019 Board meeting regarding this issue.
Questions for COO, Jason Temple
Board Chair Cindi Erickson: “What remaining work is there on the dams? We were cited. Had some findings. We’ve remedied a lot of those findings. What work remains on the dams? Do you want to come up?”
COO Temple: “We had a letter from the NRC that gave us a list. That does an inspection every year on every single dam that we have and they just list the few deficiencies. The majority of them [sic] was vegetation and we’ve got all that squared away. Everything has been mowed. Everything has been burned, as far as vegetation control.”
Temple: “There are some big items such as on Lake Pineda. There’s that concrete spillway. It needs some substantial rehab. There’s a couple of holes in the walls that allow the water to leak out to the dam. That causes erosion. We’ve had engineers look at it and so it’s kind of in planning. Things like that.”
Temple: “Other things that involve concrete on some of the spillways. We are still, haven’t completed those things. But 90 to 95 percent of everything they have requested, we have completed this year and we have responded to them via letter, showing before and after pictures.”
Temple: And so, we’ve done a good job of giving them a good progress report and this is usual business. We’ll have everything caught up, probably sometime next year.”
Director Diana Podawiltz: “I live near the pit. So I am very curious as to dates regarding control burns. I haven’t smelled or seen any evidence of any burning taking place, yet. I know that it was going to start sometime in December and we are half-way through. I was wondering if you had an update on that?”
Temple: “Sure, sure thing. We’ve just got all the approvals from the state. We had to actually get the county judge to sign off on it this year. Some new laws. We are planning to get that started very soon. We just completed the Durango culvert rehab project which tied up all the staff. I would expect to see this get started sometime next week and usually, we put blowers on it so we can get it done within a couple of weeks and be done with it for the year. But we’ll try to get this done before the end of the year.”
CEO Nalley: “I would just say, please let’s not do that on Christmas.”
Temple: “Most likely it will be after Christmas, we’ll probably start. That’s a good point.”
More questions for COO Temple (Cortez Dam)
A little later at the December Board meeting, the dam situation was again broached. This time by Director Medica, who specifically inquired about Cortez Dam. What follows is a transcription of the conversation:
Director Mike Medica: “I am going to give Jason another chance to look [indecipherable]. The Board got an email about Cortez Dam. Can you come up and address that real quick?”
Nalley: “Have you seen that, Jason? Okay.”
COO Temple states Lake Cortez Dam is in great condition
Temple: “I think it was about a month ago or a couple of weeks that Arkansas Democrat-Gazette had an article in the paper about all the hazardous dams – lake dams that were rated potentially hazardous and they listed Lake Cortez. Because we have three dams here, DeSoto, Cortez, and Balboa that we are doing the Emergency Action Plan for that are high hazard dams [indecipherable]. And they said it has some deficiencies in it and I got some phone calls about it. One about the spillway, the concrete [indecipherable], the vegetation, and some erosion.”
Temple: “If you click on the little map part of that article, online, it says the dam is in good condition and then it kind of misleads everybody a little bit, in that area. The dam is in great condition. It has some maintenance items which we have attended to on the vegetation and the erosion. The spillway, if you’ve ever looked at it, it’s still in great shape, but just at the very end of it, there was a washout years ago. It’s [indecipherable]. It’s not eroding. It’s fine, but it’s kind of one of those big items that catch their attention. And it’s not one of those things that has a very high cost to benefit ratio. It would cost a lot of money to put some concrete in there and it really wouldn’t do any good because it is a non-erosional area. So that was that issue. Thank you for letting me address that.”
Common Property and Forestry Manager needed
HSVPOA is advertising for a Common Property and Forestry Manager. One of the necessary qualifications for this position is: “Basic knowledge of Lake Dam and Spillway Maintenance and coordinating the proper maintenance in order to be in compliance with permit requirements and state regulations from the Arkansas Natural Resources Commission.”
Job Title: Common Property and Forestry Manager
Department: Public Works Department
Reports To: Superintendent of Street Maintenance
FLSA Status: Non-Exempt
Pay Grade: 08
Approved By: CEO
Approved Date: 12-03-19
Liability of HSVPOA in the event of a dam failure
HSVPOA is us. In the event of a catastrophic dam failure, and loss of property and/or life, the POA can be held responsible if we are proven to be negligent. That means WE are ultimately responsible, as members of HSVPOA.
The Dam Safety Guidance Manual for Arkansas Dam Owners discusses “general principles concerning liability and the operation of reservoirs. Liability in specific instances, however, is highly dependent upon the nature and construction of the dam, the particular circumstances surrounding the accident, the owner’s action or failure to act, and the jurisdiction in which the reservoir is located. In the event of a dam failure, the most commonly used theories to be pursued in litigation are negligence and strict liability. The liability of an owner of a reservoir is considered general civil (“tort”) liability. A tort is simply a civil wrong for which an injured party may recover damages from the responsible party. In most circumstances, simply causing damage is not a sufficient basis for the imposition of liability. Negligence must accompany the injury before liability is incurred. However, negligence is not a fixed concept; it has been modified and changed by court decisions over the years.
Safety Guidance Manual for Arkansas Dam Owners
Dam-Safety-Guidance-Manual-for-Arkansas-Dam-OwnersHappy 2020 to all of Hot Springs Village!
Here’s to hoping we get all the dam issues solved quickly! It appears the POA has addressed some of these issues and is continuing to address the remainder. It is of the utmost importance to maintain our infrastructure and these needs should come first.
I hope everyone had a Merry Christmas or Happy Hanukkah. Have a safe, productive and Happy New Year from Hot Springs Village People!
By Cheryl Dowden, December 27, 2019
Photography by Joe Dowden
Mary Odom
12/27/2019 — 6:23 pm
Thank you for sharing this with us and hopefully they will get these issues resolved sooner rather than later
Frank Shears aka Bubba
12/27/2019 — 6:26 pm
Excellent article. Thank you for posting this. This is information we, as POA Members, need to know about.
Anonymous
12/27/2019 — 8:57 pm
Don’t expect to see the truth about E-Coli at our beaches lake water or the poor condition of our highly hazardous dams in the new marketing budget. Turn up the radio to drown out the faulty brake squeaking. Nothing to see here, just keep moving along folks. Spend the disposable cash on a pool while borrowing for infrastructure necessities.
HSVP C
12/28/2019 — 9:28 am
Lakes Management monitors our lakes for E. Coli. I believe it was last summer when this practice began and that previously the monitoring was done on the state level.
We don’t have highly hazardous dams. We have high-hazard dams and that terminology is used for ALL dams, no matter the condition, where there is a potential for loss of life if the dam fails.
What is important here is that the POA is addressing dam maintenance issues and Mr. Temple has stated they plan to address the rest of the issues next year. – Cheryl
Anonymous
12/28/2019 — 10:58 pm
Exactly, Lakes management monitors our lakes for E-Coli Since last summer AFTER the State closed Cortez Lake, addresses our dams AFTER they become recognized as 1 of 25 poorestly maintained Highly Hazardous Dams in Arkansas. All the while spending our disposable cash on pools while borrowing to pay for the necessary infrastructure.
Julie
12/28/2019 — 4:48 am
I believe Troon has a dam maintenance division. Would highly recommend a secret contract with them. Problems solved.
Chipmunk
12/29/2019 — 7:45 am
Dam! Julie, what a great idea. Troon redeux.
But no worries, POA is hiring a new Manager to keep an eye on things. As I read the job description I noticed that the job is not only a Manager but it is also non-exempt. This means he or she will be paid overtime. How nice. This “Manager” also needs to know how to operate heavy equipment. Interesting.
Seems to me that all of our ratings from the inspection agency should have all been “Good”, not just “Acceptable” with deficiencies noted. Isn’t that why we have been paying a CEO and COO all these big bucks all these years? Or, maybe they just don’t know how to operate heavy equipment.
Hey, maybe the new guy (or gal) will get a bonus too if the dams don’t collapse under his watch.
Man from the clouds
12/30/2019 — 6:22 am
you have just picked up the can opener wait till you open the can chipmunk
Chipmunk
12/30/2019 — 4:19 pm
Not to worry, man from the clouds. Word is the POA is figuring out how to put some fenced patios along the dams to fully comply with Arkansas ABC laws. That way we can all enjoy a beverage as we watch the water flow out the cracks.
Anonymous
12/30/2019 — 11:11 pm
The POA will keep their finger in the dam until next year, that will hold it.